Pre‑Order Quality Checklist: What to Confirm Before Production Starts


Use this before you place the PO. It aligns engineering, purchasing and the supplier on the same page so production starts cleanly and ships on time.

1) Product and standard

  • Grade + standard + form (e.g., ASTM A240 304, sheet; or EN 10025 S235J2, plate)
  • Acceptable equivalents (list them) and priority

2) Dimensions and tolerances

  • Nominal sizes with units
  • Thickness/OD/ID/width/length tolerances (numbers or ASTM A480/EN 10051 ref.)
  • Flatness/camber/ovality/squareness where relevant
  • Edge: mill/slit/debur/chamfer; bevel angle if needed

3) Finish and cleanability

  • Finish code (2B/BA/No.4/HL/galvanized G/Z or AZ value)
  • Ra target (if hygiene matters)
  • Film protection or interleave

4) Drawings and cutting/forming

  • Latest drawing/DXF filename + revision date
  • Full cut list: QTY × L × W × T (or OD × WT × L)
  • Grain direction; bend lines and minimum inside radius
  • Nesting rules: minimum web, kerf allowance, micro-joints, edge quality

5) Welding/machining (if any)

  • Process and filler (MIG/TIG/laser), heat input limits and interpass temperature
  • Post-weld treatment: pickling/passivation, grinding/polishing steps

6) Quality documentation and tests

  • MTC EN 10204 3.1 required? (heat numbers must match piece IDs)
  • NDT scope: UT/ET/PT/RT/Hydro with acceptance criteria
  • Third-party inspection points (if any)

7) Packaging and corrosion protection

  • Method by form: coil/sheet/plate/tube; VCI/oil/barrier wrap and desiccant
  • Pallet/crate spec (IPPC), stacking and labels

8) Shipping marks and documents

  • HS code, consignee/notify, marks template
  • Commercial invoice, packing list, COO template; special certs if needed

9) Terms and timeline

  • Incoterms 2020 + payment schedule
  • Start/finish windows, booking cut-off date
  • Approval SLA: drawings/samples within 24–48 h; single decision owner

10) Change control

  • Spec freeze date; changes trigger new lead time and price
  • One shared change log

Sign-off table (copy/paste)

Item Buyer Supplier Date
Specs + tolerances ____
Finish + Ra ____
Cut list + DXF ____
MTC + tests ____
Packing plan ____
Docs & marks ____
Timeline & terms ____

FAQs

Q: Can we write “standard tolerance”?
A: List numbers or cite the exact table; “standard” varies by mill.

Q: Do we need 3.1 MTC for every order?
A: Only where properties/traceability are critical—but decide before production.

Q: Oil or VCI for sea freight?
A: VCI for clean unpack/precision parts; oil for rough plate/bars.